Prediction / Transformer lead times shorten as new winding capacity lands

Transformer lead times shorten as new winding capacity lands

Modelled new capacity against lead times, and got it wrong.

Confidence
55%
Status
Wrong
Made
19 May 2026
Resolves
30 Sep 2026
Proved wrong if
Median quoted lead time unchanged or longer at the resolution date.
Settled by
Published utility procurement schedules.

Resolved 30 Sep 2026

Lead times were flat to slightly longer. I counted announced capacity rather than commissioned capacity, and two of the three new lines had not started shipping. The error was in the input, not the model — which is the more embarrassing kind.